KORAK
|
NALOGA
|
NOSILEC
|
ROK
|
TRAJANJE
|
|
|
FAZA 1
|
|||||
|
1
|
CELOVITA ANALIZA PROSTORA – UVEDBA V DELO in
STROKOVA PRESOJA, OBRAZLOŽITEV IN UTEMELJITEV POBUDE
|
IZDELOVALEC IN OBČINA
|
30 DNI
|
30 DNI
|
|
|
FAZA 2
|
|||||
|
2
|
IZDELAVA OSNUTKA
|
IZDELOVALEC
|
20 DNI
|
20 DNI
|
|
|
3
|
PRIRPAVA GRADIVA ZA PRIDOBITEV PRVIH MNENJ NUP
|
IZVAJALEC + VLOGA OBČINA
|
7 DNI
|
||
|
4
|
TEH. PREGLED MOP IN ODDAJA GRADIVA NA STREŽNIK
|
MOP
|
8 DNI
|
8 DNI
|
|
|
5
|
VLOGE ZA PRIDOBITEV PRVIH MNENJ RAZPOŠLJE OBČINA
|
OBČINA
|
NASLEDNJI DAN PO POTRDITVI GRADIVA S STRNI MOP
|
3 DNI
|
|
|
6
|
PRIDOBIVANJE PRVIH MNENJ
|
MIN 30 DNI
|
|||
|
7
|
VLOGA ZA CPVO
|
OBČINA
|
PO PRETEKU 35 DNI OD POSREDOVANJA VLOG ZA 1 MNENJA
|
||
|
PODFAZA CPVO (ČASOVNO POKRIVA Z ANALIZO PRVIH MNENJ)
|
|||||
|
7.1.
|
PRIDOBITEV ODLOČBE ZA CPVO
|
||||
|
7.2.
|
IZDELAVA OKOLJSKEGA POROČILA
|
IZDELOVALEC OKOLJSKEGA POROČILA
|
90 DNI OD SEZNANITVE O POTREBI IZDELAVE CPVO
|
30 DNI
|
|
|
7.3.
|
IZDELAVA DODATKA
|
||||
|
7.4.
|
PRIDOBITEV SKLEPA O USTREZNOSTI OP
|
MOP
|
SKLADNO S POSTOPKOM CPVO
|
30 DNI
|
|
|
7.5.
|
DOPOLNJEN OSNUTEK SPREMEMB IN DOPOLNITEV OPN+OP
|
IZDELOVALEC
|
60 DNI PO PRIDOBITVI
IN USKLADITVI PRVIH MNENJ NUP TER SKLEPA O USTREZNOSTI OP
|
/
|
|
|
PODFAZA ANALIZA PRVIH MNENJ (ČASOVNO POKRIVA Z IZDELAVO CPVO)
|
|||||
|
6.1.
|
ANALIZA PRVIH MNENJ
|
OBČINA, NUP, IZDELOVALEC
|
PREDVIDOMA 30 DNI (ODVISNO OD VSEBINE PRVIH MNENJ)
|
30 DNI
|
|
|
6.2.
|
USKLAJEVANJE PRVIH MNENJ
Z RAZLIČNIMI NUP
|
OBČINA, NUP, IZDELOVALEC
|
30 DNI
|
||
|
ZAKLJUČEK OBEH PODFAZ
|
|||||
|
6.3.
|
DOPOLNJEN OSNUTEK SPREMEMB IN DOPOLNITEV OPN+OP
|
IZDELOVALEC
|
60 DNI PO PRIDOBITVI IN USKLADITVI PRVIH MNENJ NUP TER SKLEPA O USTREZNOSTI OP
|
60 DNI
|
|
|
FAZA 3
|
|||||
|
8
|
JAVNA OBJAVA JAVNE RAZGRNITVE IN JAVNE OBRAVNAVE + OBVESTILO LASTNIKOM TANGIRANIH ZEMLJIŠČ
|
OBČINA
|
15 DNI
|
15 DNI
|
|
|
9
|
JAVNA RAZGRNITEV SD OPN
IN OP + JAVNA OBRAVNAVA
|
OBČINA
|
30 DNI
|
||
|
10
|
PRIPRAVA STALIŠČ DO PRIPOMB, PREDLOGOV
IN POTRDITEV
|
OBČINA IN OBA IZDELOVALCA (OPN IN OP)
|
ODVISNO OD KOLIČINE PRIPOMB, PREDLOGOV IN POTREDITEV – PREDVIDOMA 30 DNI
|
60 DNI
|
|
|
11
|
PRIPRAVA GRADIVA ZA PRVO OBRAVNAVO NA SEJI OBČINSKEGA SVETA
|
OBČINA
|
10 DNI PO PREJEMU GRADIVA
|
10 DNI
|
|
|
opomba
|
ODVISNO OD SEJE OBČINSEKGA SVETA
|
OBČINA
|
/
|
/
|
|
|
FAZA 4
|
|||||
|
12
|
PRIPRAVA PREDLOGA OPN
|
IZDELOVALEC
|
30 DNI PO POTRDITVI DOPOLNJENEGA OSNUTKA IN STALIŠČ DO PRIPOMB NA SEJI OS
|
30 DNI
|
|
|
13
|
POSREDOVANJE PREDLOGA OPN
|
VLOGA OBČINA
|
1 DAN
|
1 DAN
|
|
|
14
|
ODGOVOR MOP IN ODDAJA GRADIVA NA STREŽNIK
|
MOP
|
8 DNI
|
8 DNI
|
|
|
15
|
VLOGE ZA PRIDOBITEV DRUGIH MNENJ V PRVEM KROGU RAZPOŠLJE OBČINA
|
OBČINA
|
NASLEDNJI DAN PO PRIDOBITVI GRADIVA
|
1 DAN
|
|
|
16
|
PRIDOBITEV DRUGEGA MNENJA + OPREDEILTEV SPREJEMLJIVOSTI SPREMEMB
IN DOPOLNITEV OPN
V POSTOPKU CPVO IN ODLOČBA MOP
|
NUP
|
30 DNI
|
30 DNI
|
|
|
FAZA 5
|
|||||
|
17
|
USKLAJEVANJE DRUGIH MNENJ NUP
|
OBČINA, IZDELOVALEC, NUP
|
PREDVIDOMA 30 DNI (ODVISNO OD VSEBINE DRUGIH MNENJ)
|
30 DNI
|
|
|
18
|
PONOVNA VLOGA ZA PRIDOBITEV DRUGIH MNENJ
|
VLOGA: OBČINA
|
45 DNI
|
45 DNI
|
|
|
19
|
VLOGE ZA PRIDOBITEV DRUGIH MNENJ V DRUGEM KROGU RAZPOŠLJE OBČINA
|
OBČINA
|
NASLEDNJI DAN PO PRIDOBITVI GRADIVA
|
1 DAN
|
|
|
20
|
ODGOVOR MOP IN ODDAJA GRADIVA NA STREŽNIK
|
MOP
|
8 DNI
|
8 DNI
|
|
|
21
|
PRIPRAVA USKLAJENEGA PREDLOGA
|
IZDELOVALEC
|
30 DNI PO PREJEMU POZITIVNIH DRUGIH MNENJ
|
||
|
22
|
PRIRPAVA GRADIVA ZA SEJO OBČINSKEGA SVETA
|
OBČINA IN OBA IZDELOVALCA (OPB IN OP)
|
10 DNI
|
||
|
23
|
PRIPRAVA SPREJETEGA ODLOKA (ČISTOPISA) ZA OBJAVO (LEKTORIRANJE) IN OBJAVA
V URL
|
OBČINA
|
30 DNI PO SPREJEMU OZIROMA PO DOGOVORU
|
||
|
FAZA 6
|
|||||
|
24
|
KONČNA PREDAJA GRADIVA
|
IZVAJALEC
|
10 DNI PO OBJAVI V URL
|
10 DNI
|
|